7 VERIFICATION REQUIREMENTS
7.1 General
AVI-2086/CREATED/R
The contractor shall propose the verification program, which shall be subject to agreement by Astrium
Ltd.
AVI-2087/CREATED/R
The verification process shall demonstrate conformance to applicable requirements. A satisfactory
completion of the verification process is the basis for a contractual acceptance of the product by the
customer.
The requirements of this specification and of the specifications referenced therein shall be subject to
formal verification close out.
As far as equipment or software is rebuilt from lower level test equipment (e.g., unit tester), the formal
verification of the corresponding functions may be achieved by demonstration of successful use in
lower level integration and testing.
7.2 Test Equipment
AVI-2089/CREATED/R
Adequate test equipment and simulators shall be made available to support the verification process.
AVI-2090/CREATED/R
This test equipment need not necessarily be deliverable and may therefore be recruited from the
suppliers laboratory inventory. Of particular importance is the simulation of the communication
interface with the RTS and CCS. These shall be fully representative on all protocol layers including
the physical interface.
7.3 Verification Program
AVI-2092/CREATED/R
The subcontractor shall establish a verification program that assures that
The product is in compliance with the specified requirements.
The design is qualified.
The product is in agreement with the qualified design, free from workmanship defects and acceptable for use.
Qualification is defined as the proof that a design fulfils the requirements with adequate margin. For reused
software modules / components acceptance test reports / qualification test reports may be used to
demonstrate compliance with the requirements stated. The subcontractor shall not be required to rerun
acceptance / qualification tests for existing, reused software. In case reference is made to already
performed and existing acceptance / qualification in the frame of other space programs, requirements
tracing of the above RTS requirements to the existing test procedures and test result has to be provided as
well as the existing test procedures and test reports themselves.